Shreveport will undergo significant lane closures on Knight Street as a major reconstruction project commences. The southbound lane will be closed from South Point Parkway to Flyer Drive starting Tuesday at 6 a.m. This closure is expected to last for six weeks. The project, originally budgeted at $3.5 million, has expanded to approximately $6.5 million due to inflation and aims to enhance road safety and aesthetics. Residents are encouraged to contact city engineering for updates regarding the ongoing work.
Shreveport is set to experience lane closures on Knight Street as part of a long-awaited reconstruction project. Starting at 6 a.m. on Tuesday, the southbound lane of Knight Street will be closed from just south of South Point Parkway to Flyer Drive. This closure is expected to last for a duration of six weeks.
The ongoing reconstruction project has been marred by numerous delays over the past 12 years. While the southbound lane is affected, northbound traffic on Knight Street will not encounter disruptions. The overall construction is anticipated to continue until September, with a substantial completion set for late summer.
This project comes in the wake of a 2011 bond issue election in which voters authorized a budget of $3.5 million for upgrades to Knight Street. However, the escalating costs caused by inflation have increased the budget to approximately $6.5 million. These funds will be utilized for a comprehensive overhaul of the roadway, including the installation of new lighting and sidewalks.
Reconstruction work began last summer, with an estimated total of 260 working days required to complete the project. As building disruption continues, residents are encouraged to stay informed and reach out for any construction-related inquiries. For more information, residents can contact the city engineering staff at (318) 673-6000 or email Adam Duvernay.
Project Overview
- Location: Knight Street, Shreveport
- Closure: Southbound lane from South Point Parkway to Flyer Drive
- Duration: Six weeks
- Start Date: 6 a.m. on Tuesday
- Expected Completion: Late summer
- Original Budget: $3.5 million
- Current Budget: $6.5 million
- Work Days: 260 working days planned
- Additional Features: New lighting and sidewalks
Background Context
The Knight Street reconstruction project was initially planned in response to the need for infrastructural improvements in the area. Following the bond issue passed in 2011, the project faced inevitable delays primarily due to funding discrepancies and inflation costs. As cost projections ballooned from the original allowances, the city sought to build a better and safer roadway for the community over the years.
This extensive reconstruction project is part of a broader effort to enhance road safety and accessibility in Shreveport, ensuring that residents have improved infrastructure to utilize for their daily commutes. The improvement of Knight Street aims not only to better facilitate traffic flow but also to enhance the aesthetics of the area with the introduction of new sidewalks and lighting.
FAQ Section
What are the details of the Knight Street closure?
The southbound lane of Knight Street will be closed from just south of South Point Parkway to Flyer Drive, beginning at 6 a.m. on Tuesday for six weeks.
What impact will this have on traffic?
Northbound traffic on Knight Street will not be affected by the closure.
How much is the reconstruction project costing?
The project is currently budgeted at about $6.5 million, which has increased from the original budget of $3.5 million due to inflation.
Who can residents contact for more information?
Residents can reach the city engineering staff at (318) 673-6000 or can email Adam Duvernay.
Deeper Dive: News & Info About This Topic
HERE Resources
Shreveport Implements Measures for School Zone Traffic Safety
New Law Enhances Safety in School Zones
Local Businesses Sunshine Health Market and Bon Lagniappe to Close
Caddo Parish School District Enhances Safety for Students
Knight Street Reconstruction to Begin Soon in Shreveport
Shreveport Starts Construction on Knight Street Southbound Lane
Knight Street Reconstruction Progresses in Shreveport
Shreveport Moves Forward with Ford Street Repaving
Additional Resources
- Eastern Progress: Doing Better Business with Louisiana State Licensing Board for Contractors
- Wikipedia: Construction
- Shreveport-Bossier Advocate: Construction of State Office Building
- Google Search: Shreveport construction updates
- KTBS: Shreveport Man Charged with Contractor Fraud
- Google Scholar: Construction Fraud in Louisiana
- Shreveport-Bossier Advocate: Knight Street Construction Update
- Encyclopedia Britannica: Road Construction